Keller Banner
File #: 21-184    Version: 1
Type: Consent Status: Agenda Ready
File created: 4/6/2021 Meeting Body: City Council
On agenda: 4/20/2021 Final action:
Title Search: Consider a resolution approving the construction bid from Canary Construction, Inc. of Lewisville, Texas, for the Big Bear Central Interceptor Phase 2 Project, for the Public Works Department; and authorizing the City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.
Attachments: 1. 0422021_Big Bear Central Interceptor_Resolution, 2. 0422021_Big Bear Central Intecepter_Big Bear Creek Interceptor map, 3. 04202021_Big Bear Central Intecepter_Bid Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:                     Mark R. Hafner, City Manager

From:                     Alonzo Liñán, Public Works Director

Subject:                     

Title

Consider a resolution approving the construction bid from Canary Construction, Inc. of Lewisville, Texas, for the Big Bear Central Interceptor Phase 2 Project, for the Public Works Department; and authorizing the City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.

Body

 

Action Requested:                     

Consider a resolution approving the construction bid from Canary Construction, Inc. of Lewisville, Texas; for the Big Bear Central Interceptor Phase 2 Project in the amount of $525,474.00.

 

Background:                     

During development of The Gean Estates, a 15-inch sanitary sewer line was installed and connected to the current sanitary line running on Keller Parkway to serve the areas north of Johnson Road.  Further development has resulted in an increased demand on the sanitary sewer system and this replacement will meet these requirements.

The project will replace approximately 1000 lineal feet of 6-inch and 12-inch sanitary sewer line with 15-inch sewer line installed by various methods of construction such as horizontal directional drilling and open trenching to meet future needs.  The work also includes water service replacements and associated asphalt and concrete pavement repair along the North side of Keller Parkway.  A Location Map for the project is included.

Two (2) qualifying bids were received at Keller Town Hall on March 24, 2021 for this project.  A bid summary is included showing the range of bid amounts.  City staff has reviewed the low bidder’s qualifications, bonding capacity and references and recommends Canary Construction Inc., of Lewisville, Texas be awarded the bid in the amount of $525,474.00 with construction to be completed within 150 calendar days.

 

Financial Impact:

Funding is included in the Water/Wastewater Capital Improvement Project Fund with funding provided by the Water/Wastewater Utility fund and Wastewater Impact Fee fund.

 

Citizen Input/Board Review:                     

Not applicable.

Legal Review:                       

The City Attorney has reviewed and approved this resolution.

 

Alternatives:                     

City Council has the following alternatives:                       

-                     Approve as submitted

-                     Approve with changes

-                     Denial

 

Council Action:                     

Staff recommends approval of the proposed resolution as presented.