To: Aaron Rector, Interim City Manager
From: Alonzo Liñán, Director of Public Works
Subject:
Title
Consider a resolution authorizing a payment to North Texas Contracting, Inc. of Keller, Texas; for the emergency repair of a 10” sanitary sewer line failure adjacent to 811 Barbara Lane, for the Public Works Department; and authorizing the Interim City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.
Action Requested:
Approve a payment to North Texas Contracting, Inc. of Keller, Texas; for the emergency repair of a 10” sanitary sewer line failure adjacent to 811 Barbara Lane, in the amount of $164,237.00.
Background:
On May 25th, staff was notified that a sewer line break had occurred adjacent to 811 Barbara Lane. Due to the anticipated scope and a satisfactory prior work history, North Texas Contracting was selected to perform the emergency repairs. Staff engaged with North Texas Contracting, who mobilized a crew and was onsite within two hours of the initial failure report. Their crews performed a temporary repair ahead of a projected rain event, with permanent repairs completed in the ensuing days. This payment authorization encompasses both the temporary and permanent repairs.
Financial Impact:
Funds are budgeted in the Wastewater Collection operations budget with funding provided by the Water & Wastewater Utility Fund.
Alternatives:
City Council has the following alternatives:
- Approve as submitted
- Approve with changes
- Denial
Council Action:
Staff recommends approval of the proposed resolution as presented.