Title Search: Consider a resolution rejecting all proposals received for the Water System Capital Improvement Plan Phase 3 Project, for the Public Works Department, and further authorizing the City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.
Attachments: 1. 120324_SWIFT3Rejection_Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:                     Aaron Rector, Interim City Manager

From:                     Alonzo Liñán, Director of Public Works

Subject:                     

Title

Consider a resolution rejecting all proposals received for the Water System Capital Improvement Plan Phase 3 Project, for the Public Works Department, and further authorizing the City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.

Body

 

Action Requested:                     

Approve a resolution rejecting all proposals received for the Water System Capital Improvement Plan Phase 3 Project received on September 25, 2024, and further authorizing the Interim City Manager to re-advertise the project.

 

Background:                     

On September 25, 2024, the City of Keller Public Works Department received five (5) qualified proposals for the Water System Capital Improvement Phase 3 Project. The lowest price of the five proposals received, for $8,853,937.00, is well beyond the project budget.  As a result, City staff recommends that the City Council reject all proposals and authorize the Interim City Manager to re-advertise the project.

Legal Review:                       

This item has been reviewed by the City Attorney.

 

Council Action:                     

Staff recommends approval of the item as presented.