Title Search: Consider a resolution approving the bid from Central North Construction, LLC., of Allen, Texas, for the construction of the US 377 landscape enhancements Green Ribbon project for the Parks and Recreation Department and authorizing the City Manager to execute all related documents.
Attachments: 1. US377 Median Improvements Construction Contract Resolution.pdf, 2. 0081-02-079 US377 GR Concurrence of award.pdf, 3. 0081-02-079_US377 GR_State Letter of Authority.pdf, 4. 0081-02-079_US377 GR_FPAA.pdf, 5. 0081-02-079_US377 GR_Engineer's Estimate.pdf, 6. 0081-02-079_US377 GR_Bid Tab.pdf, 7. 0081-02-079_US377 GR_Bid Analysis Letter.pdf, 8. 0081-02-079_Keller US377_Letter of Recommendation.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:                     Aaron Rector, City Manager

From:                     Jordan Dawson, Interim Director of Community Services

Subject:                     

Title

Consider a resolution approving the bid from Central North Construction, LLC., of Allen, Texas, for the construction of the US 377 landscape enhancements Green Ribbon project for the Parks and Recreation Department and authorizing the City Manager to execute all related documents.

Body

 

Action Requested:                     

Approve a resolution approving the bid from Central North Construction, LLC., of Allen, Texas, in the amount of $261,605.30 for the construction of the US 377 landscape enhancements Green Ribbon project for the Parks and Recreation Department and authorizing the City Manager to execute all related documents.

 

Background:                     

The City was awarded up to $400,000 from TxDOT as part of the Green Ribbon program. This money is for beautification and landscaping projects along TxDOT roadways. The City has received three previous Green Ribbon awards to improve US377 through Old Town Keller and for FM1709 from Page Street to Pearson. This project continues the City’s goal to improve medians throughout the City.

 

Financial Impact:

Funding for this activity is included in the Street System Capital Improvements Project Fund with funding provided by the General Fund with TxDOT reimbursement. If unforeseen circumstances are encountered, which results in an overage of the project budget, further council action and a budget amendment may be required.

 

Legal Review:                       

The City Attorney has reviewed and approved.

 

Alternatives:                     

City Council has the following alternatives:                       

-                     Approve as submitted

-                     Approve with changes

-                     Denial

 

Council Action:                     

Staff recommends approval of the proposed resolution as presented.