File #: 20-179    Version: 1
Type: Consent Status: Agenda Ready
File created: 3/20/2020 Meeting Body: City Council
On agenda: 4/7/2020 Final action: 4/7/2020
Title Search: Consider a resolution approving the construction bid from CI Pavement of Grand Prairie, Texas; for the North Pate Orr Sidewalk Improvements Project for the Public Works Department; and authorizing the City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.
Attachments: 1. 040720_North Pate Orr_Resolution, 2. 040720_North Pate Orr_Location Map, 3. 040720_Bid summary N Pate Orr
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To:                     Mark R. Hafner, City Manager

From:                     Alonzo Liñán, Public Works Director

Subject:                     

Title

Consider a resolution approving the construction bid from CI Pavement of Grand Prairie, Texas; for the North Pate Orr Sidewalk Improvements Project for the Public Works Department; and authorizing the City Manager to execute all documents relating thereto on behalf of the City of Keller, Texas.

Body

 

Action Requested:                     

Consider a resolution approving the construction bid from CI Pavement of Grand Prairie, Texas for the North Pate Orr Sidewalk Improvements Project in the amount of $174,809.88.

Background:                     

In an effort to address pedestrian safety in areas near public facilities such as schools and parks, city staff identified missing sidewalk segments throughout the city and have prioritized those missing segments.  This project will construct a sidewalk from FM 1709 to the Keller High School campus along North Pate Orr Road.  In an attempt to keep cost down, City staff is proposing repurposing one of the existing travel lanes for sidewalk across the drainage channel.  This is the more economic option to constructing a sidewalk bridge or extending the box culverts. Work is expected to start in May 2020 and coincide with school being out of session. Staff has coordinated with Keller ISD representatives.

Eleven (11) qualifying sealed bids were received on March 11, 2020.  A bid summary is attached showing the bid amounts. City staff has reviewed the low bidder’s qualifications, bonding capacity and references and recommends CI Pavement of Grand Prairie, Texas be awarded the bid in the amount of $174,809.88 with construction to be completed within forty-five (45) calendar days.
                                          

Financial Impact:

Funding is included in the Fiscal Year 2019-20 budget.

Citizen Input/Board Review:                     

Not applicable

 

Legal Review:                       

The City Attorney has reviewed and approved.

Alternatives:                     

City Council has the following alternatives:                       

-                     Approve as submitted

-                     Approve with changes

-                     Denial

 

Council Action:                     

Staff recommends approval of the proposed resolution as presented.